Starting to construct the natural gas pipeline

The-Pori-Terminal-August-2015.jpg

In Finland Skangas start the construction of the natural gas pipeline connected to Pori LNG terminal

Skangas is having a natural gas pipeline build from the LNG terminal under construction in Tahkoluoto, Pori, Finland, to Kaanaa industrial park. The pipeline construction project begins in early August 2015, and the connection pipeline is due for commissioning in May 2016.

The main gas user in the Kaanaa industrial park is Huntsman Pigments and Additives Oy. Once completed, the pipeline will also provide other industrial customers with access to natural gas.

Made from polyethene (PE), the connection pipeline will be around 12 km long and have an external diameter of 355 mm. The pipeline will cross varied terrain, including under roads and railways, and also be laid on the seabed over a section of approximately 3.2 km at a depth of cover of around 1 m.

The main contractor selected for the pipeline construction and installation work is Destia Ltd, which will also use the services of local contractors. 

The average number of personnel working on the project will be 30.